Blacklisting of a contractor by Gujranwala Electric Supply Company was allowed by the Hon'ble Lahore High Court primarily on the ground that neither was any show cause notice nor was an opportunity of a hearing afforded to the petitioner before its blacklisting through a nonspeaking order.

In the case of Nizami Construction Company Vs. Chief Executive Officer, Gujranwala Electric Supply Company (2005 CLC 366), a writ petition against the blacklisting of a contractor by Gujranwala Electric Supply Company was allowed by the Hon'ble Lahore High Court primarily on the ground that neither was any show cause notice nor was an opportunity of a hearing afforded to the petitioner before its blacklisting through a nonspeaking order.

Part of judgment 

IN THE ISLAMABAD HIGH COURT, ISLAMABAD (JUDICIAL DEPARTMENT)

Musawar Kamal VS FOP etc
Writ Petition-3212-2019 | -
Honourable Mr. Justice Miangul Hassan Aurangzeb